Background/Discussion
West Graham Avenue is in need of reconstruction. The project extends approximately 1,360 feet in length, from High Street to Fairmount Avenue. This street segment is a boulevard with a 30-foot wide raised median with trees, located within an existing right-of-wayof 100-feet. West Graham extends east – west with a single lane of travel in each direction and parallel parking allowed along the outside curbs in most locations. It is a residential area with houses fronting the street, with the majority having individual driveways. West Graham is a collector roadway that serves as a connection to East Graham and S. 1st Street.
It is likely that the original construction of West Graham Avenue dates to 1907, the same time Fairmount Avenue was constructed. The roadway and utilities are old, in poor condition, and are due for replacement.
The project will include new street pavement and sidewalks, drainage improvements, and new sanitary sewers. Council Bluffs Water Works will replace a portion of their water main as part of the project. The other utilities in the area will also be investigated for replacement.
This Federal-aid project was included in the FY25 CIP and includes a budget of $2,405,000 in STBG funds and $1,250,000 in Local Option Sales Tax funds.
The engineering and right-of-way acquisition costs associated with the project will be paid by the City.
Temporary construction easements will be required from a portion of the adjacent properties to properly tie in driveways, grading, service walks, and steps. See attached exhibit for easement locations.