| | | | | | | | Council Communication
Department: Public Works Admin
Case/Project No.: PW24-26
Submitted by: Matthew Cox, Public Works Director | Resolution 24-220
ITEM 3.E. | Council Action: 8/26/2024 |
|
| | | | | | | | Description
Resolution accepting the work of DPS, LLC as complete and authorizing the release of retainage after 30 days if no claims are filed in connection with the Council Bluffs Recycle Center Scale Paving project. Project# PW24-26 |
|
| | | | | | | | Background/Discussion
The outbound scale at the City’s Recycling Center was installed in 1997 and was near the end of its useful life. This scale was replaced with a new outbound scale installed by Scales, Sales, and Service, the same company responsible for the new inbound scale installed in January 2023.
This project constructed the additional paving needed around the scale location, finalizing the improvements to both the inbound and outbound scales. Traffic flow and safety at the facility’s entrance and exit have been significantly enhanced.
The cost for this project was included in the Recycling Center Operating Budget.
|
Original Contract Amount |
$52,340.12 |
|
Change Orders (+11.09%) |
$6,226.35 |
|
Final Contract Amount |
$58,566.47 |
|
Less Previous Payments |
$55,638.15 |
|
Retainage Due Contractor |
$2,928.32 |
The project was completed on time and the Contractor did not receive any non-compliance notices.
|
|
| | | | | | | | Recommendation
Approval of this resolution accepting the work of DPS, LLC as complete and authorizing the release of retainage after 30 days.
|
|
|