| | | | | | | | Council Communication
Department: Public Works Admin
Case/Project No.: PW24-21
Submitted by: Matthew Cox, Public Works Director | Resolution 24-194
ITEM 5.F. | Council Action: 7/8/2024 |
|
| | | | | | | | Description
Resolution accepting the bid of Western Iowa Utilities (Hildreth Landscape Inc.) for the Kanesville Sanitary Sewer Extension. Project # PW24-21 |
|
| | | | | | | | Background/Discussion
On June 20, 2024 bids were received through the City bidding software Ion Wave as follows:
|
|
Division I |
Division IV |
|
|
|
General |
San. Sewer |
Total |
| Western Iowa Utilities (Hildreth landscape Inc.) Council Bluffs, IA |
|
$154,636.95 |
$1,155,205.30 |
$1,309,842.25 |
| Compass Utility LLC, Council Bluffs, IA |
|
$152,832.72 |
$1,289,477.96 |
$1,442,310.68 |
| United Utilities and Excavation LLC Council Bluffs, IA |
|
$139,697.75 |
$1,651,205.00 |
$1,790,902.75 |
| Neuvirth Construction, Inc. Blair, Nebraska |
|
$243,505.51 |
$1,553,698.63 |
$1,797,204.14 |
| Vrana Construction, Omaha, NE |
|
$208,794.27 |
$1,640,755.00 |
$1,849,549.27 |
| Valley Corporation, Valley Nebraska |
|
$287,418.64 |
$1,609,808.20 |
$1,897,226.84 |
| McCarthy Trenching, LLC Avoca, IA |
|
$262,378.70 |
$1,786,051.23 |
$2,048,429.93 |
| Judds Bros. Construction Co. Lincoln, NE |
|
$221,778.90 |
$1,904,920.00 |
$2,126,698.90 |
| Carley Construction LLC Council Bluffs, IA |
|
$251,206.80 |
$1,967,732.60 |
$2,218,939.40 |
| Bluffs Paving and Utility Co. Inc. Crescent, IA |
|
$380,603.92 |
$2,178,492.49 |
$2,559,096.41 |
| Boomernag Corp. Anamosa, IA |
|
$272,102.00 |
$2,967,010.00 |
$3,239,112.00 |
| Engineer's Opinion (HGM) |
|
$251,158.00 |
$1,864,704.50 |
$2,115,862.50 |
Future commercial developments near the I-80 Interchange at Kanesville Boulevard will require sanitary sewer improvements. The proposed sewer will tie into the existing sanitary sewer on the west side of the BNSF railroad tracks south of Kanesville Boulevard, and extend to the east just west of the I-80 westbound on-ramp. This will provide service to the open ground at the southwest quadrant of the I-80 Interchange.
A second phase will extend the sewer east of I-80 to serve future development to the east.
The project was included in the FY24 CIP with ARPA identified as the funding source. ARPA Revenue Loss funds have been authorized for the engineering and construction costs of the project.
| The project schedule is as follows: |
Award |
July 8, 2024 |
|
Construction Start |
Summer/Fall 2024 |
|
|
| | | | | | | | Recommendation
Approval of this resolution to accept the bid of Western Iowa Utilities (Hildreth Landscape Inc.) for the Kanesville Sanitary Sewer Extension project.
|
|
|