| | | | | | | | Council Communication
Department: Public Works Admin
Case/Project No.: PW23-06A
Submitted by: Matthew Cox, Public Works Director | Resolution 24-162
ITEM 3.G. | Council Action: 6/10/2024 |
|
| | | | | | | | Description
Resolution setting a public hearing for June 24, 2024 at 7:00 p.m., for Levee Certification Project, Geotechnical MR_6. Project # PW23-06A |
|
| | | | | | | | Background/Discussion
The City of Council Bluffs owns or sponsors multiple levee segments which encompass the City Federal Levee System, providing flood protection from the Missouri River, Mosquito Creek, and Indian Creek. These levee systems are currently shown on FEMA floodplain maps as being accredited and are identified as providing protection from the 100-year flood or 1% annual chance flood event.
In order to maintain the level of protection identified on the FEMA Flood Insurance Rate Map, it is necessary to provide documentation to FEMA that complies with the requirements of 44 CFR 65.10. If the levees are not certified, they will be de-accredited and FEMA will begin the process of updating maps. Areas previously protected by the levees will be identified as flood-prone.
In order to meet the criteria for levee certification, improvements to each of the levee systems will be necessary. The purpose of the Geotechnical MR_6 project is to resolve seepage deficiencies along the Missouri River. The project will construct large berms along the land side of the levee.
This project was included in the FY23/FY24 CIP and with a budget of $16,000,000. Construction costs will be paid with GO Bonds programmed for levee improvements and Iowa Flood Mitigation Program funds.
| The project schedule is as follows: |
Set Public Hearing |
June 10, 2024 |
|
Hold Public Hearing |
June 24, 2024 |
|
Bid Letting |
July 25, 2024 |
|
Award |
August 12, 2024 |
|
Construction Start |
September 1, 2024 |
|
Construction Complete |
June 30, 2026 |
|
|
| | | | | | | | Recommendation
Approval of this resolution to set the Public Hearing. This project will improve the levee system to meet the criteria for certification.
|
|
|