Description

Resolution approving the plans and specifications for the TSL Intermodal Container Freight Station in Council Bluffs.

 

Background/Discussion

The City of Council Bluffs and TSL Company Holdings, Ltd. applied for grant funding under the Linking Iowa’s Freight Transportation Systems (LIFTS) Program.  TSL has secured $1,536,000 in construction funding through the LIFTS Program.  LIFTS requires administration of the project by a local municipality. Iowa DOT and TSL requested that the City fill that role.  

A development agreement between the City of Council Bluffs and TSL was signed in November of 2021.

TSL has purchased 54-acres at 116 N. 29th Street and an existing building at 2427 South Avenue and plans to relocate 38 new full-time positions to Council Bluffs from their Omaha facility. When fully operational, the economic activity generated by this project is expected to add approximately $9.7 million to the local economy each year.

TSL plans to build an intermodal container freight station that will enhance the Iowa Interstate Railroad intermodal ramp by centralizing intermodal support operations. The estimated project cost for the initial phase is $2,000,000.  TSL will be responsible for any remaining costs above the grant amount.  Future additions will be funded by TSL Company Holdings, LTD. 

The Iowa DOT will let the project.

 

The project schedule is as follows: Hold Public Hearing May 20, 2024
Bid Letting June 18, 2024
Award July\August 2024
Construction Start September 2024
Recommendation

Approval of the resolution to approve the plans and specifications for the TSL Intermodal Container Freight Station. 

 