| | | | | | | | Council Communication
Department: Public Works Admin
Case/Project No.: PW24-11
Submitted by: Matthew Cox, Public Works Director | Resolution 23-260
ITEM 4.B. | Council Action: 9/25/2023 |
|
| | | | | | | | Description
Resolution approving the plans and specifications for the N. 28th Street Storm Sewer Rehab, Phase IV. Project #PW24-11 |
|
| | | | | | | | Background/Discussion
The N. 28th Street drainage basin limits are approximately I-29 to Avenue F and N. 10th Street to N. 33rd Street. This area is roughly 580 acres. The existing storm sewer network in this area was constructed in the 1950’s and is undersized causing frequent street flooding. The existing storm sewer interceptors are located along Avenue L, North 24th Street, and Avenue K. In the past, high ground water conditions have caused several of the storm interceptors to fail, resulting in costly emergency repairs.
Phase I is complete and consisted of construction of a new 84” storm sewer pipe under I-29. The Phase II project is complete and included the study of the drainage basin to identify and prioritize future projects and connected the 84” storm sewer to the N. 28th Street storm sewer pump station. Phase III is nearly complete and included the extension of the 84” storm sewer from south of the interstate to N. 28th Street.
Phase IV will include the replacement of the storm sewer interceptor in Avenue L from 2700 Avenue L to 28th Street. The project will require the reconstruction of the roadways and sanitary sewer. The phased approach of this rehabilitation project is based on prioritizing the roadways with existing storm sewer interceptors, frequent flooding areas, and infrastructure that is in poor condition needing immediate replacement.
The project was included in the FY24 CIP with funding from Local Option Sales Tax and Sewer Funds. The preliminary project budget is $4,000,000.
| The project schedule is as follows: |
Hold Public Hearing |
September 25, 2023 |
|
Bid Letting |
|
October 31, 2023 |
|
Award |
|
November 13, 2023 |
|
Construction Start |
March 1, 2024 |
|
|
| | | | | | | | Recommendation
Approval of this resolution to approve the plans and specifications for the N. 28th Street Storm Sewer Rehab, Ph. IV. |
|
|