| | | | | | | | Council Communication
Department: Public Works Admin
Case/Project No.: PW24-15
Submitted by: Matthew Cox, Public Works Director | Resolution 23-213
ITEM 3.C. | Council Action: 8/14/2023 |
|
| | | | | | | | Description
Resolution setting a public hearing for August 28, 2023 at 7:00 p.m. for Pavement Resurfacing. Project # PW24-15 |
|
| | | | | | | | Background/Discussion
The Pavement Resurfacing project is intended to rehabilitate streets that need maintenance, but do not require a full reconstruction. The selected streets are good candidates for surface milling and hot-mix asphalt overlays.
Two streets have been identified for this project. The outside lanes of 23rd Avenue from S. 35th Street to 23rd Avenue, and North Broadway from East Orchard Avenue to Gunn Avenue.
This project was included in the FY24 CIP and is funded with $750,000 in Local Option Sales Tax funds.
| The project schedule is as follows: |
Set Public Hearing |
August 14, 2023 |
|
Hold Public Hearing |
August 28, 2023 |
|
Bid Letting |
September 14, 2023 |
|
Award |
September 25, 2023 |
|
Construction Start |
October 1, 2023 |
|
|
| | | | | | | | Recommendation
Approval of this resolution. The project will improve roadways in need of rehabilitation.
|
|
|