| | | | | | | | Council Communication
Department: Public Works Admin
Case/Project No.: PW23-20
Submitted by: Matthew Cox, Public Works Director | Resolution 23-208
ITEM 6.D. | Council Action: 7/24/2023 |
|
| | | | | | | | Description
Resolution accepting the bid of Peterson Contractors, Inc. for the Perry Road Culvert Replacement. Project # PW23-20 |
|
| | | | | | | | Background/Discussion
On July 13, 2023 bids were received through the City bidding software Ion Wave as follows:
|
Division I General
|
Total
|
|
| |
|
|
|
Peterson Contractors, Inc., Reinbeck, IA
|
$656,532.10
|
$656,532.10
|
|
|
|
|
|
United Utilities & Excavation, Council Bluffs, IA
|
$685,245.60
|
$685,245.60
|
|
|
|
|
Neuvirth Construction, Inc., Blair, NE
|
$946,296.54
|
$946,296.54
|
|
|
|
|
|
Engineer's Opinion
|
$585,610.00
|
$585,610.00
|
The Perry Road culvert is an old concrete box culvert that is in need of replacement. The existing structure has exposed rebar, spalling concrete, and missing wing walls. Replacement of the culvert is needed to maintain Perry Road and the access it provides to the properties north of the culvert.
This project was included in the FY23 CIP with funding from Local Option Sales Tax.
| The project schedule is as follows: |
Award |
July 24, 2023 |
|
Construction Start |
September 2023 |
|
|
|
|
|
| | | | | | | | Recommendation
Approval of this resolution for award to Peterson Contractors, Inc. for the Perry Road Culvert Replacement Project.
|
|
|