| | | | | | | | Council Communication
Department: Public Works Admin
Case/Project No.: PW24-09
Submitted by: Matthew Cox, Public Works Director | Resolution 23-201
ITEM 5.E. | Council Action: 7/10/2023 |
|
| | | | | | | | Description
Resolution accepting the bid of Compass Utility, LLC, for the East Manawa Sewer Rehab, Phase XII. Project # PW24-09
|
|
| | | | | | | | Background/Discussion
On June 29, 2023, bids were received through the City bidding software, Ion Wave, as follows:
|
Division I General
|
Division II Pavement
|
Division IV San. Sewer
|
Total
|
|
|
Compass Utility, LLC, Council Bluffs, IA
|
$221,535.56
|
$87,664.75
|
$733,530.22
|
$1,042,730.53
|
|
|
|
|
|
|
|
Engineer's Opinion (EGA)
|
$200,552.00
|
$74,317.50
|
$774,677.50
|
$1,049,547.00
|
The area of East Manawa is very flat with open ditches. There are no storm sewers in this area and the streets are thin asphalt or seal-coated rock roads. During rainfall events, considerable surface ponding occurs due to the poor drainage.
The rehab program also includes installation of new sanitary sewers utilizing a vacuum system.
Phase I and II of the program included Huron Circle from Navajo to north of Osage Street. Phase III of the program was construction of the sanitary sewer vacuum pump station. Phase IV was the first phase of vacuum sewer installation with the porous pavement and subdrain system on Huron Circle from Navajo to just west of Blackhawk Street. Phases V through IX continued the rehab and completed Huron Circle, Blackhawk Street, Osage Street, Victor Street, Aztec Street, East Navajo Street and extended the vacuum sewer along Navajo Street. Phase X included Pickard Lane from Hall Walk (Alley) south to Navajo Street. Phase XI includes Pickard Lane from Hall Walk (Alley) north to Navajo Street. Phase XI is scheduled to be complete in July 2023.
Phase XII includes extending the vacuum sewer along the east side of Navajo Street from the pump station at the intersection of Mohawk and Navajo Street to Comanche Street and along the south side Comanche Street from Navajo Street to Apache Street.
This project is included in the FY24 CIP and includes a budget of $700,000 in Local Option Sales Tax funds. The Division IV costs will be paid with Sewer funds.
| The project schedule is as follows: |
Award |
July 10, 2023 |
|
Construction Start |
August 2023 |
|
|
|
|
|
| | | | | | | | Recommendation
Approval of this resolution. This project continues the infrastructure improvements for the neighborhood.
|
|
|