Background/Discussion
The Council approved $125,000 in the FY24 CIP for the Fairmount Park Road Erosion Repair and Strom Water Management project. The scope of the project is to install storm drain pipe and inlets in order to prevent rainwater from washing out the embankment along Fairmount Park Road. The embankment and within less than five feet of the road is eroding with a few sink holes developing.
The engineer's cost opinion for the work is $80,355.00 and is within budget.